City of Columbus Franklinton

Meeting Minutes for November 19, 2007

Pre-Open House Project Team Meeting

Attendees

  • Nick Shultz - EMH&T
  • Larry Creed - EMH&T
  • Terry Stewart - City of Columbus
  • Dan Burden - Walkable Communities

West Broad Street

  • Dan Burden recommended considering the following 3-Lane section:
    • 14-Foot center two-way left turn lane
      • Extra width provides flexibility to widen travel lanes later, if needed
      • Colorize the asphalt to distinguish from travel lanes
    • (2) 6-Foot parking lanes on the outsides
      • Larger width would reduce valuable space without added safety benefits
    • (2) 7-Foot bike lanes between parking and travel lanes
      • Colorize the asphalt to distinguish from travel lanes
      • End at roundabouts and possibly add ramps and trail around
    • (2) 10-Foot travel lanes
  • Curb extensions should be extended to accommodate front and rear doors of bus
  • Improvements should enable some turn restrictions to be removed to lessen cut-through traffic and speeding on neighborhood streets

Traffic Circles

  • Dan Burden thought the cost estimate was very high – should only consist of adding a curbed island in the middle of the intersection
  • Substantial curb reconstruct and right-of-way takes were needed because of tee intersection

Sidewalks

  • Missing sidewalk segments should be prioritized
  • School areas should have highest priority